60MWh DC-Side Energy Storage System Solution

2026-03-02

1. Project Overview

This solution is designed for the construction of a 60MWh lithium iron phosphate energy storage system consisting of 12 standard 5MWh liquid-cooled battery containers. The system is connected to the grid at 35kV voltage level, mainly applied for grid-side peak shaving, renewable energy supporting facilities, or large industrial and commercial users. Adopting the DC-side parallel connection scheme, the DC sides of the 12 battery containers are collected and connected to the DC side of PCS (Power Conversion System), which reduces AC circulating current and improves system efficiency.

2. Core Product Parameters

The energy storage container system adopts 314Ah battery cells, with battery PACKs configured in a 2P52S series-parallel connection. Each battery cluster includes 8 PACKs and is matched with 1 high-voltage box. The DC circuits of 6 battery clusters are integrated to the isolating switch of the collection and control cabinet to form 1 DC high-voltage circuit. Each energy storage container is equipped with 1 DC high-voltage circuit, as well as auxiliary equipment such as liquid cooling unit, dehumidifier, BMS (Battery Management System) and fire protection system.

2.1 Main Component Configuration of Energy Storage Container

Table 1 Main Component Configuration

No.

Component

Quantity

Remarks

1

Battery Cluster / 2P416S

6 clusters

Electric energy storage device

2

BMS System

1 set

For battery management and monitoring

3

High-voltage Box

6 sets

Primary circuit on-off protection, data detection and processing

4

Busbar Distribution System

1 set

For primary current collection and power supply distribution

5

Liquid Cooling Unit

1 unit

For regulating the temperature of battery PACKs

6

Fire Protection System

1 set

Aerosol fire extinguishing device + gas detector + smoke/temperature sensor + water fire protection

7

Dehumidifying Air Conditioner

2 units

For regulating temperature and humidity inside the container

8

Converter (PCS)

6 units

5MW, 2 units in parallel for 5MW output

9

High-voltage Transformer

6 units

Step-up from 0.315kV to 35kV

2.2 Key Technical Parameters of Energy Storage Container

Table 2 Key Technical Parameters

No.

Category

Item

Specification

Remarks

1

Electrical Performance

Nominal Capacity

5015kWh

/

2

-

Rated Voltage

1331.2V

3.2V per cell

3

-

Voltage Range

1040V ~ 1497.6V

2.5V ~ 3.6V per cell

4

-

Rated Current

1884A

/

5

-

Standard Working Condition

0.5P

2500kW

6

-

Cycle Life

≥8000 times

@70% SOH EOL, 95% DOD, 25℃

7

-

DC-side Efficiency

≥94%

25℃

8

-

Auxiliary Power Voltage Range

380VAC±10%, 50/60Hz

Three-phase five-wire system

9

Communication

Communication Interface

Ethernet, RS485, CAN

/

10

Battery Parameters

Cell Capacity

314Ah

/

11

-

Configuration

12P416S

/

12

-

Number of Battery PACKs

48

/

13

 

Wiring Mode

Quick Plug

/

14

Basic Parameters

Dimension (H*W*D)

6058x2438x2896mm

/

15

-

Color

RAL 9003

Optional

16

-

Weight

≈42T

/

17

-

Anti-corrosion Grade

C4/C5

/

18

-

Protection Grade

IP55

/

3. PCS and Step-up System Parameters (Configured by DC-side Scheme)

Table 3 PCS and Step-up System Parameters

Item

Parameter

PCS Configuration

6 units of 5MW centralized energy storage converters

DC-side Input

1100-1500V DC (connected to the DC bus after current collection)

AC-side Output

315V / 690V (adjusted according to PCS outlet voltage)

Transformer

6 units of 5MVA oil-immersed transformers (step-up to 35kV)

Topology Structure

Each 2 battery containers (10MWh) connected to 1 unit of 5MW PCS

4. Station Topology

4.1 Description of Main Electrical Wiring Topology

Battery Array: 12 units of 5MWh containers, divided into 6 groups (2 units per group).

DC Current Collection: The 2 battery containers in each group are connected in parallel through the DC circuit breaker cabinet and connected to the DC bus (DC 1500V).

Inversion Unit: The DC bus is connected to 1 unit of 5MW PCS.

Step-up and Grid Connection: The AC output of PCS is connected to a 5MVA transformer (0.315/35kV), and connected to the 35kV bus through the high-voltage switch cabinet after step-up.

4.2 Station Topology Diagram

(Attachment: Topology Diagram of 60MWh DC-Side Energy Storage Station)

Battery Energy Storage System

5. Construction and Installation Scheme

5.1 Civil Foundation Phase (Approx. 30 days)

Site Leveling: Compaction treatment for the estimated 100m x 80m site, with the requirement of ground bearing capacity > 10t/m².

Foundation Pouring:

• Battery container foundation: Adopt strip foundation or independent bearing platform with pre-embedded cable trench sleeves. The foundation surface height must be higher than the local 50-year flood level or water accumulation level.

• Cable trench: Set up longitudinal and transverse cable tunnels for laying DC cables (attention to separation of strong and weak current).

Grounding Grid: Lay hot-dip galvanized flat steel to form an annular grounding grid with grounding resistance < 0.5Ω.

5.2 Equipment Installation Phase (Approx. 20 days)

Container Hoisting:

• Use a 150-ton mobile crane for unloading and positioning.

• Installation sequence: Hoist the remote containers first, then the near ones to avoid path obstruction.

• After the container is positioned, calibrate the level with a laser level, then fix it (welding or clamping of anchor bolts).

High-voltage Equipment Installation:

PCS and transformers are generally integrated in the step-up cabin (or independent platform) for busbar connection and insulation testing.

Cable Laying:

• DC cable: Adopt special DC cable with a voltage resistance of DC 1.8kV (e.g., YJV-1.8/3kV), with attention to the color distinction of positive and negative poles (red/black) and lightning protection grounding.

• Communication cable: Lay Category 6 shielded network cables or optical fibers along the special bridge of the cable trench, with a distance of > 300mm from the power cable.

5.3 Commissioning Phase (Approx. 15 days)

Single Unit Commissioning: Test the BMS communication, battery cell voltage and internal resistance, and fan start/stop of each battery container one by one.

System Commissioning: PCS no-load operation -> PCS on-load operation -> EMS (Energy Management System) logic test (charging and discharging response time < 40ms).

Grid Connection Test: Conduct anti-islanding protection test and power qua

6. Detailed Technical Parameters

6.1 Battery System

• Cell Specification: 3.2V / 314Ah (1C charge/discharge, energy density > 165Wh/kg)

• Assembly Mode: 2P52S (one battery PACK, voltage 166.4V) -> 8 battery PACKs in series (container voltage 1331.2V)

• Energy Efficiency: ≥ 94% (including auxiliary power consumption, 0.5C charge/discharge)

• SOC Accuracy: ≤ 3%

• Auxiliary Power Supply: AC 380V, 50Hz, power consumption of each container is about 8kW (during cooling)

6.2 PCS System

• Topology Structure: Three-level IGBT topology

• Efficiency: ≥ 98.5% (including transformer)

• Response Time: ≤ 30ms

• Cooling Mode: Air cooling / Liquid cooling (customized according to manufacturer)

• Protection Functions: DC overvoltage, AC overcurrent, insulation detection, anti-islanding protection

6.3 Monitoring and Communication

• Communication Protocol: IEC 61850 (power station level), Modbus TCP/IP (internal system)

• Main Equipment: BMS (Battery Management System), PMS (Power Management System), EMS (Energy Management System)

• Data Collection: Single cell voltage and temperature; single battery cluster current; grid connection point frequency and harmonics.

7. Maintenance and Servicing Scheme

7.1 Daily Inspection

Table 4 Daily Inspection Items

Frequency

Item

Content

Daily

Appearance Inspection

Check if the container is deformed, the cabinet door is locked, and the sound and light alarm is normal.

Daily

BMS Monitoring

Check the background for sudden changes in single cell voltage/temperature and SOC jump.

Weekly

Temperature Control System

Check the normal operation of air conditioners/liquid cooling units, blockage of radiators, and coolant pressure.

Weekly

Cleaning

Clean the container filter screen to prevent heat dissipation failure caused by dust accumulation.

7.2 Regular Special Maintenance

Table 5 Regular Special Maintenance Items

Cycle

Item

Detailed Operation

3 Months

Terminal Tightening

Carry out infrared temperature measurement on the connections of DC-side circuit breakers, fuses and copper bars, and spot-check whether the torque is loose.

6 Months

Insulation Test

Test the insulation resistance of DC bus to ground with an insulation megger (requirement > 1MΩ).

6 Months

Fire Protection System Test

Test the sensitivity of smoke/temperature detectors, check the pressure of fire extinguishers, and conduct simulated discharge test if necessary.

1 Year

Battery Balancing

If the single cell voltage difference > 150mV, perform manual or automatic (BMS) passive/active balancing maintenance.

1 Year

PCS Dust Removal

Clean the dust in the power modules and heat dissipation air ducts inside the PCS with a high-pressure air gun.

3-5 Years

Battery Cell Consistency

Conduct a full capacity charge-discharge test, and replace the backward modules with SOH lower than 80%.

7.3 Emergency Response Plan

7.3.1 Thermal Runaway Alarm

1. Immediately disconnect the DC circuit breaker of the faulty cluster.

2. Start the exhaust system (if designed for smoke exhaust).

3. Confirm personnel evacuation and remotely start the perfluorohexanone/heptafluoropropane fire extinguishing device.

4. If the fire spreads, dial 119 and start the water spray system (ensure the electrical system is powered off to prevent electric shock).

7.3.2 Grid Fault

In case of grid flashover or frequency mutation, the PCS shall automatically switch to standby or grid-forming mode to support the grid. After the fault, check whether the PCS IGBT modules are damaged.

8. Project Economic Indicators (Estimated)

Table 6 Project Economic Indicators

Item

Indicator

Total System Capacity

60 MWh

Rated Power

30 MW (designed for 0.5C charge/discharge)

Floor Area

Approx. 5000 - 6000 square meters

Unit Investment Cost

Approx. 0.8 - 0.95 CNY/Wh (DC-side)

Estimated Total EPC Investment

Approx. 50 - 57 million CNY

Annual Operation and Maintenance Cost

Approx. 0.02 CNY/Wh/year

 


Get the latest price? We will reply as soon as possible (within 12 hours)